四虎免看黄_亚洲精品综合第一国产综合_免费福利在线观看_野花在线无码视频在线播放_精品一区二区三区日本_亚洲av禁18成人毛片一级

phone/wechat/what's app: +86-18653810085

Email: hongyuanmakela@163.com

Taian Hongyuan Geosynthetics Co., Ltd.
Tel:18653810085

Technical Services Current Position:Home > Technical Services

Precautions for GCL construction

Release time:2020-4-7    This article is read :5106 Times

GCL construction

Precautions for GCL construction

1. The site should be kept relatively dry during construction, and the base surface can be wet, but there should be no water accumulation.

2. The laying, connection and interface of the GCL should meet the design requirements and construction specifications, and be firm and stable, without hollowing, damage, slippage, warping, wrinkling and other phenomena.

3. If the impermeable blanket is damaged during the laying process, a pair of GCLs larger than the damaged surface by 30cm ~ 50cm must be cut and covered, and the surrounding area should be coated with bentonite waterproof slurry. 4. After the GCL is laid and inspected, the construction of backfill shall be carried out simultaneously to avoid trample and damage.

5. The GCLs should be stacked in the designated place on the site, and be cushioned to maintain a certain distance from the ground, and covered with plastic film to avoid rainwater immersion, sunlight and moisture.

6. If it rains during the construction process, it should be covered immediately with plastic film materials or rain shielding materials to avoid rainwater soaking and washing the waterproof layer and affecting the construction quality. When the rain is large and the bentonite swells by more than 300%, it should be laid again.

7. The equipment or truck cannot be placed directly on the GCL, and the cover must be set to work.

8. When laying, it is strictly forbidden to put an open flame or cigarette butt on any side of the GCL, and it is strictly forbidden for construction personnel to wear spike shoes.

9. During the construction, if the construction party encounters unclear drawings or the construction site does not conform to the design of the drawings, it should be notified to the designer in time and properly resolved through consultation.

10. For other unfinished matters, the national and local acceptance standards and operating specifications shall be followed during construction.

Precautions for GCL construction
Previous:Comparative analysis of several geotextile materialsnext:Construction notes of GCL

Contact Us:

WeChat public account

Taian Hongyuan Geosynthetics Co., Ltd.

Phone / Wechat / What's app:+86-18653810085

Telephone / Fax: + 86-538-6598877

Email:  hongyuanmakela@163.com

Website: www.jylilong.com

Address: Jinghua Industrial Zone, NO. 88 Leigushi Street, Taishan Industrial Park, Taian City, Shandong Province, China

Copyright? Taian Hongyuan Geosynthetics Co., Ltd.            Lugong Network Security No. 37090202000491            Lu ICP No. 16042524-1           公示信息

主站蜘蛛池模板: 炉霍县| 玉田县| 军事| 合水县| 寻甸| 偏关县| 沙河市| 咸宁市| 遵化市| 福贡县| 内乡县| 哈尔滨市| 土默特左旗| 玉树县| 加查县| 昌黎县| 水城县| 阜宁县| 绵阳市| 富裕县| 西林县| 监利县| 金沙县| 贵州省| 禹州市| 丹寨县| 彭泽县| 南陵县| 正定县| 安泽县| 会宁县| 藁城市| 阿坝县| 绍兴市| 佛山市| 伊金霍洛旗| 赤壁市| 石首市| 望奎县| 玛沁县| 留坝县|